Convergence investment status

Convergence operative status

Total solution time

Circuit Loading

Lower loading limit violation

Upper loading limit violation

Check Redundancy

Accumulated Capacity

Total Cost

Accumulated Length

Total Generation

Total Generation Deviation

Total Load Shedding

Case information

Directory name Path Execution status
optnet-example - Success

About the model and environment

Model User Version ID Architecture
OptNet 5.0.Beta29 - -

About the execution nodes

Execution type Total nodes Total processes
SEQUENTIAL 1 1

Case title

Title
SDDP

Horizon, resolution, and execution options

Case parameters optnet-example
Case type Monthly
Hourly representation ❌
Typical days representation ❌
Initial date 1/2020
Final date 12/2022
Selected series 0
Selected resolution 0
Selected systems 0

Solution strategy

Solution strategy optnet-example
Solution method Decomposition
Critical scenario criterion Greater distribution
Number of critical scenarios 1
MIP Relative gap tolerance (%) 3
MIP CPU Time limit (min) 10
Slack representation Load shedding
Slack penalty (k$/MW) 10000
Generation deviation ❌
Generation deviation type -
Generation deviation factor (%) -
Capacity deviation factor (%) -
Circuit overload Selected
Sum of circuit flow ❌
Contingency representation ❌

Dimensions

Case parameters optnet-example
Systems 1
Hydro plants 0
Thermal plants 9
Renewable plants - Wind 4
Renewable plants - Solar 4
Renewable plants - Small hydro 0
Renewable plants - Other techs 0
Renewable plants - CSP 0
Batteries 0
Power injections 0
Buses 12
AC lines 5
Transformers 0
Three winding transformers 0
DC lines 2
AC Interconnections 0
LCC converter 4
VSC Converter 0