- OptGen 1, Benders decomposition. An investment module decides the plan, SDDP evaluates its stochastic operation and returns Benders cuts, and the two iterate until the lower and upper bounds converge. Suited to long horizons with many scenarios and stages.
- OptGen 2, co-optimization. Investment and operation are solved together in a single problem, with hourly resolution on typical days and a rolling horizon, year by year. Suited to hourly variability, intra-day storage and integrated generation and transmission studies.
SDDP Platform · Expansion planning
OptGen
Generation and transmission expansion planning under uncertainty
An expansion plan has to work across many scenarios of hydrology, renewables and demand. Many planning tools reduce the number of scenarios or the time resolution to keep the problem solvable. OptGen decides which projects to build, where and when, at minimum total cost, integrated with SDDP. Its decomposition algorithms scale with high-performance computing, so studies can keep many scenarios and a detailed time resolution.
Two strategies on one platform
OptGen decides which technologies to build, where and when, at minimum total cost. It offers two strategies, both running on the SDDP database.
Data centers and large loads
Large loads such as data centers are now decision variables. OptGen decides whether, where and when they are built, and treats them in the same way as renewable candidates.
Investment cost
The construction cost in million USD, as for any expansion candidate.
Demand profile
The hourly profile of the load and its flexibility window.
Willingness to pay
A price in USD/MWh that represents the value of compute for each MWh consumed.
Battery and solar degradation
SDDP usually handles this kind of data per calendar year, but degradation depends on the entry date of each project, and in OptGen that date is a decision. A dedicated screen now relates degradation to the entry date OptGen chooses, so it does not bias the investment decisions.
Automatic firm capacity of renewables
An expansion plan has to meet a firm capacity requirement: enough capacity that the system can count on in the hours of highest need. For wind and solar, that amount depends on the mix being built.
The critical hours move with the mix
Thermal and hydro plants count for most of their installed capacity. Wind and solar count only for what they produce in the hours of highest net demand, that is, demand minus renewable generation.
Those hours change as the mix changes. With little solar, net demand peaks in the early evening, while solar plants still produce. As more solar is built, net demand falls at midday and its peak moves past sunset, and the firm capacity of solar falls.
Calculated by OptGen, year by year
A fixed value, entered once, cannot follow this change. Kept high, it lets the plan count on capacity that will not be there at the peak. Updated by hand, it has to be recalculated for every year and every mix, while the mix is what OptGen is deciding.
OptGen now calculates it year by year: it finds the hours of highest net demand of the previous year and averages the available generation of each renewable candidate over those hours. The firm capacity follows the system and the renewable mix being built.
The calculation is already used in planning studies and becomes a standard OptGen feature in SDDP 19.
Resilience days
OptGen 2 represents the hourly operation with typical days. A typical day is an average of many days and scenarios: it keeps the usual shape of the day, with the valley at midday when the sun is high.
The average also hides the unusual days. On a gloomy day, with little sun, net demand stays high from morning to night, and a system sized for the typical day may not cope with it.
Resilience days add real days to the OptGen 2 expansion problem. Each one is identified by its date and scenario, keeps all its hours, and its operation must be feasible with the planned system.
Faster convergence
Integrated generation and transmission studies with a detailed network are the hardest cases for the decomposition. SDDP 19 helps them converge.
OptGen 1 and SDDPRegularization and relaxed Benders cuts
A regularization scheme stabilizes the investment problem, and relaxed cuts, computed without the second Kirchhoff law, give it early guidance. Exact cuts then sharpen the bound. On hard cases with a detailed network, this can be the difference between converging and not.
Automatic precedence constraints for transmission projects also help these studies converge.
Transmission expansion with OptNet
OptGen already plans transmission together with generation. OptNet, its new network module, refines the transmission plan against every dispatch scenario computed by SDDP, so the plan does not rely on a few snapshots of the system.
Explore OptNetResults
A new dashboard
A more flexible dashboard, integrated with the Results tab, shows the operational dispatch behind each expansion decision.
OptGen 2 results in the Results tab
A new Results module loads, plots and navigates every opt2_*.csv result of the OptGen 2 operational module, which used to need custom scripts. The SDDP results workflow now covers OptGen 2.
OptGen is part of SDDP 19
Install SDDP 19 to run OptGen, or talk to our team about your study.
Documentation and support
The OptGen documentation is in the PSR Knowledge Hub, and the changelog lists every change in this version.